Monday, 29 November 2010

The Varnished Truth w/e Dec 04 10

Action on every front again this past week…

Lightning team:
George has completed the new seat support system and Chris has been creating and installing side deck gussets with loads resolved in-line this time. Scott has just about finished scraping and sanding the varnish dribbles from the inside bottom.

     Skiff Front:
Jim has refreshed the stain and begun the varnishing inside one of the skiffs and it is really looking amazing now. Scuff it up before the next few coats and it should be done next week.

The second skiff should be right behind it.

Oars have been ordered and will be here in 4 to 6 weeks.

Shepherd team:
the scraping of the bottom prior to repainting is about 30% complete.


Other tasks for this week:

Scrapper II and Wings need a winter covers and we have the covers. Scrounge up some ridge poles, sawhorse brackets and some 2x4's and we can get this done.

See you in the Boatshop!